Buckingham Group the main contractor for the electrification of the railway through Hindley has ceased trading. Losses on football stadiums appears to be the problem.

Started: 20th Aug 2023 at 12:17

Posted by: GOLDEN BEAR (6556) 

Gaffer ,
Where does that leave the bridge repairs at Hindley then ? Also are they the same people who have dealings with Kilhey Court???? G.B.

Replied: 20th Aug 2023 at 13:36
Last edited by GOLDEN BEAR: 20th Aug 2023 at 13:36:58

Posted by: First Mate (2395)

3 DAYS AGO

Network Rail are doing the bridge repair work.

Replied: 20th Aug 2023 at 13:40
Last edited by First Mate: 20th Aug 2023 at 13:46:31

Posted by: Tommy Two Stroke (15433)



Replied: 20th Aug 2023 at 14:40

Posted by: mortarmillbill (929)

TTS
2024? It is supposed to be opening in a couple of weeks on the 1st Sept 2023.
Not that I am complaining as it is so peaceful.

Replied: 20th Aug 2023 at 17:11

Posted by: Tommy Two Stroke (15433)

That is on google maps with the traffic layer switched on, but I suppose it could be a mistake, and it will be open by the 1st of September

On the other hand, maybe the suppliers are going to repossess their new bridge and leave a big gap on Ladies Lane

Replied: 20th Aug 2023 at 17:20

Posted by: Owd Codger (3126)

First Mate

Correct, but the work on the electrification may also involve plant supplied by one of their sub contractors like Balfour Beatty, Colas, Volker Rail etc.

Replied: 21st Aug 2023 at 08:44

Posted by: Tommy Two Stroke (15433)

They are bringing in Murphy to finish the job LINK

How do you confuse an Irishmon ?

Place two shovels against a wall and tell him to take his pick

Replied: 27th Aug 2023 at 13:46

Posted by: Owd Codger (3126)

Nothing wrong with Murphys, who did a superb job installing gas at my property while my next door neighbour had it done by British Gas who made a right mess. I even had to fill in a hole with concrete for him which they had left and never came back to do despite being requested numerous times.

Perhaps if Murphy's had been given the bridge job, it would have been completed by now!

It's hardly the Ribblehead Viaduct, is it!

Replied: 28th Aug 2023 at 08:09

Posted by: Tommy Two Stroke (15433)

The bridge is showing on Google Maps has being open with delays, which looks to be probably temporary traffic lights.

Replied: 10th Sep 2023 at 10:18

 